 |
Space Flight Systems Directorate
Activities Report
January 25 - Feb. 5, 2009
ADVANCED FLIGHT PROJECTS OFFICE
ISS Research Program
InSPACE Operations Began on ISS with Installation of Hardware
into the Microgravity Science Glovebox (MSG): The
Investigating the Structure of Paramagnetic Aggregates from
Colloidal Emulsions-2 (InSPACE-2) flight hardware was successfully
installed in the Microgravity Science Glovebox (MSG) on January
27, 2009, by ISS Increment 18 Commander, Mike Fincke. Following
installation of the hardware, Mike performed the first of seven
additional science runs scheduled for InSPACE-2. On Friday,
January 30, 2009, Increment 18 flight engineer, Sandy Magnus,
performed three additional runs on the InSPACE hardware. All
operation runs were performed with near real-time video down-linked
to the InSPACE-2 team in the Telescience Support Center (TSC)
in Bldg 333. The research associate for the InSPACE-2
principal investigator, Paula Vasquez (U of Delaware), tied
in remotely.
The objective of the InSPACE-2 experiment is to continue
the InSPACE-1 studies to determine the lowest energy configurations
of the three dimensional structures of a magnetorheological (MR)
fluid in a pulsed magnetic field. MR fluids are a class of
smart materials capable of changing visco-elastic properties. These
objectives improve limb and dextrous motion in robotic components
and human-robotic interfaces for EVA suits.
Contact: MAH/Nancy Hall, (216) 433-5643
InSPACE-3 CDR Kickoff Meeting Held on February
3, 2009. A Critical Design Review (CDR) kickoff meeting
was held on February 3, 2009, for the Investigating the Structure
of Paramagnetic Aggregates from Colloidal Elipsoids-3 (InSPACE-3)
flight experiment. Project Manager, MAH/Nancy Hall, presented
an overview of the experiment and hardware, along with the design,
safety, and verification approaches. Project Scientist,
RET/Bob Green, presented an overview of the science, and Engineering
Lead, Chuck Bunnell (ZIN), presented the new fluid sample vial
assembly design.
The CDR kickoff presentation was well received by the engineering
panel. A number of design issues were brought up including
a suggestion for using an alternate method of sealing the fluid
sample vials. The engineering review panel is in the process
of preparing a report and a list of Requests for Action (RFAs).
The objective of the InSPACE-3 experiment is to continue InSPACE-1
and InSPACE-2 studies to determine the lowest energy configurations
of the three-dimensional structures of a magnetorheological (MR)
fluid in a pulsed magnetic field. In particular, InSPACE-3
will investigate 3-D structures formed by non-spherical super-paramagnetic
colloidal particles in these pulsed magnetic fields. InSPACE-3
will utilize the InSPACE-1 experiment hardware presently on ISS,
and consist of new fluid samples and a new vial assembly design
that allows two simultaneous orthogonal views of 3-D structure formation.
Contact: MAH/Nancy Hall, (216) 433-5643
NASA Employees are Contributing Authors to Frontiers
of Propulsion Science.
MAH/Nancy R. Hall was one of several NASA employees who co-authored
a chapter in the book Frontiers of Propulsion Science edited
by RPP/Marc Millis and Eric W. Davis from the Institute for Advance
Studies at Austin, Texas. Nancy co-authored and contributed
to Chapter 19, “Investigating Sonoluminescence as a Means
of Energy Harvesting,” along with co-authors RHS/John Wrbanek,
RHS/Gustave Fralick, and RHI/Susan Wrbanek. Nancy was the
Project Scientist for a NASA Research Announcement grant that focused
on single-bubble sonoluminescence in the Fluid Physics and Transport
Branch and discussed some of that research in the chapter. She
also reviewed another chapter in the book. Frontiers of
Propulsion Science covers NASA's Breakthrough Propulsion Physics
Project from 1996-2002 as well as other related works to provide
starting material for readers on numerous visionary topics. The
book was published in 2009 by the American Institute for Aeronautics
and Astronautics (AIAA) as Volume 227 in the Progress in Astronautics
and Aeronautics book series.
Contact: MAH/Nancy Hall, (216) 433-5643
The Microgravity Acceleration Measurement System
(MAMS) team at Glenn Research Center (GRC) supported the analysis
of the excessive vibration that occurred during the reboost of
the International Space Station (ISS) using the Service Module
on January 14, 2009.
MAMS collected acceleration data in support of the reboost of the
ISS on January 14, 2009, and was requested to analyze the acceleration
data and provide plots to the Johnson Space Center (JSC) Structures
and Dynamics group in the weeks following the event. The JSC
Structures and Dynamics group would like to understand the January
14, 2009, reboost event before the next reboost. MAMS collected
the acceleration data from the reboost event and forwarded the data
to the Space Station Structures and Dynamics group at JSC. JSC
uses the MAMS acceleration data to confirm their ISS structure models
based on ISS center of gravity and structural dynamics.
Contact: MAH/Robert Hawersaat, (216) 433-8157
Advanced Capabilities Project Office
ETDP - Propulsion and Cryogenics Advanced Development (PCAD)
- Lander Ascent Main Engine (AME) Technology Development Contract
Altitude Engine Critical Design Review. A Critical
Design Review (CDR) for the altitude configuration AME was held
at Aerojet facilities in Sacramento on January 28-29, 2009,
to present the final design and analyses for the Aerojet ablative
5,500-lbf workhorse liquid oxygen/liquid methane (LOX/LCH4)
engine. Components reviewed included the injector assembly,
the altitude chamber and ablative liner design, and the chamber/nozzle
interface. NASA will attach a Shuttle OME nozzle extension
to the chamber built at Aerojet for testing at the White Sands
Test Facility test stand 401 in the fall. Several issues
have previously been identified for the altitude engine, including
concerns about exceeding the inter-laminar shear capability
of the ablative liner for long duration tests and an internal
leak in the first injector manifold. NASA personnel conducted
an engineering review board for each of these issues in December
and January to review the possible recovery paths recommended
by Aerojet, and the selected recovery paths and impact on schedule
were also discussed at the CDR. Sea level testing is now
scheduled to begin in late May 2009. While this will still
meet the milestone of sea level test completion by the end of
June, the injector manufacturing issues have removed all slack
from the schedule. The CDR was supported by a wide range
of organizations from within NASA GRC as well as personnel from
Marshall Space Flight Center, Johnson Space Center, White Sands
Test Facility and Edwards Air Force Base. The purpose of this
risk-reduction activity is to demonstrate and validate performance
levels for a Lunar Lander liquid oxygen/liquid methane ascent
engine and to address high priority risks for LOX/LCH4 AME (reliable
ignition, fast start).
Contactss: MAC/Todd Peterson, (216) 433-5350 and RPP/Diane
Linne, (216) 977-7512
ETDP - Cryogenic Fluid Management (CFM) Project - Presented
technologies that supported both Altair and Ares V to the Technology
Prioritization Process (TPP) Panel Discussions held on January
30, 2009. Altair had provided seed money in 2008 to
determine the feasibility of propellant scavenging, and as a result
has baselined the process in their design. Funding from
Altair was discontinued with the intent that ETDP would continue
the work to bring the process to a TRL 5-6 by the Preliminary
Design Review (PDR). CFM presented the follow-on work required. The
TPP Panel reprioritized propellant scavenging, and it is expected
to be funded in FY11 and be included in the PPBE11 cycle. CFM
also presented required work for Ares V. CFM seeks to address
three main aspects that must be successful to mitigate risk for
Ares V: 1) High performance Multi-Layer Insulation (MLI)
at extremely large scale, 2) Heat rejection in low-g at extremely
large scale (Thermodynamic vent system (TVS), and 3) Large scale/low-g
fluid/thermodynamics for mixing/pressure control. The TPP
Panel did not reprioritize this task, however, they asked for
more information, and it will likely be included in PPBE11. Contact: MAC/Susan
Motil, (216) 433-8589
ETDP - Energy Storage Project - Reviewed
the Lunar Surface Systems (LSS) studies on energy storage and
power generation at JSC on February 3. ATK, Hamilton-Sundstrand,
and Battelle presented results of studies awarded under the LSS
Broad Area Announcement for innovative methods of energy storage
and power generation on the lunar surface. Concepts for
utilizing solid oxide fuel cells, power beaming, and thermal wadis
were presented. The purpose of the review was to provide
technical feedback to the contractors prior to the final presentations
on February 25 at the Department of Commerce, Washington, DC.
Contact: MAC/Carolyn Mercer, (216) 433-3411
Science Project Office
In-Space Propulsion Technology Project Office - Patent Office
Examiner Interview Conducted. The claims contained
in NASA patent application "Magnetic Circuit for Hall Effect
Plasma Accelerator" by Manzella, et al. were discussed
with an examiner and supervisor from the United States Patent
and Trademark Office (USPTO) at their office in Washington,
D.C. The examiner agreed that, with proposed amendment,
the claims of this invention would overcome the prior art of
record and be rendered allowable. These amended claims
will be submitted in response to the current USPTO Final Office
Action no later than February 12, 2009. This invention
was made to enable reduced-cost electric propulsion systems
for deep space robotic space exploration in support of the Science
Mission Directorate’s In-Space Propulsion Technology Project.
Contacts: DEP/David Manzella, (216) 977-7432), MAS/Eric J.
Pencil (216) 977-7463
SPACE OPERATIONS PROJECT OFFICE
Communications Navigation and Networking re-Configurable
Testbed (CoNNeCT)
( Project Manager - Konstantinos Martzaklis):
- The CoNNeCT Team is continuing to develop Concept
of Operations (CONOPS) scenarios through dedicated workshops. These
scenarios are key in understanding information flow to and from
the ground and payload and will provide insight into requirements
decomposition and traceability from Level I requirements down
to lower, ‘box’ level specifications. These
scenarios are key to completing the project’s requirements
decomposition and traceability needs in preparation for PDR.
- The project has also been working closely with
performing organizations to close on its workforce gaps. Workforce
issues, primarily at GRC and to a certain extent at other Centers,
continue to challenge the project’s ability to accomplish
its work especially in preparation for its upcoming Preliminary
Design Review (PDR) in April. Workforce challenges include
filling existing gaps, shoring up skill mix issues with existing
staff and addressing new requirements and underplanning since
institutional workforce validation back in the fall of 2008. If
these critical staffing needs aren’t met, the project’s
schedule and readiness for PDR will be negatively impacted. The
Project Manager and Chief Engineer have been working this issue
and the PM briefed the Center Management Council on January 26
as to its urgency.
- The System Requirements Review (SRR) for the Harris
Software Defined Radio (SDR) was held on January 29 via WebEx
at GRC. Subsystem requirements for the radio were presented
including platform/hardware requirements as well as requirements
associated with the radio Operating Environment (OE) and its waveforms. Harris
presented its plans on how requirements would be addressed. The
Harris radio is one of three SDR’s planned to be flown on
the CoNNeCT Payload.
- The project gave Authority to Proceed (ATP) to
the vendor for procurement of the payload antenna pointing system
(APS). The APS is an integrated system to be delivered to
GRC and will point a high gain Ka-band dish antenna along with
a medium gain S-Band antenna to the Tracking and Data Relay Satellite
System for two-way connectivity between the payload and the ground. Contract
award is expected the week of February 2, 2009.
- Payload Integration JSC Meetings: The project
Payload Integration Lead visited JSC and held a number of meetings
associated with integration of the payload with ISS and the Japanese
Exploration Agency (JAXA) H-II launch vehicle. The CoNNeCT-ISS
Payload Integration Agreement (PIA) final draft has been agreed
to and has been submitted for final review and signature. This
will establish the agreement for formal integration of the payload
with ISS and JAXA.
- Members of the project Systems Engineering (SE)
team and Engineering’s Systems Engineering organization
hosted a demonstration of IBM’s Rhapsody requirements modeling
tool. The tool is being investigated to assist in modeling
and validating project requirements and decomposition. It
interfaces with DOORS- the project’s requirements database
tool. Rhapsody would facilitate proper requirements decomposition
is accomplished through a disciplined approach allowing requirements
flow-down, validation and traceability.
- CoNNeCT has received commitment from the GSFC
EXPRESS Logistics Carrier (ELC) personnel to share their source
code for the ELC simulator. D. Varga will act as the point
of contact with Lily Bashar and Oscar Gonzalez at GSFC to receive
the software and documentation. GSFC is sending this software
with the stipulation that they will not be able to provide any
support at this time since they haven’t been given any funding
to support the activity. This support, along with the software
and documentation, is listed in the Payload Integration Agreement
between International Space Station and CoNNeCT.
Contact: Denise Varga/DPS,
(216) 433-5190
- Wind River personnel were at GRC on January
28 and 29, to install their Lab Diagnostics tool and conduct
training of the GRC CoNNeCT software team. Though expensive,
the CoNNeCT payload avionic software team feels this tool will
significantly increase the efficiency of developing and testing
flight software. The tool allows testing and debugging
of code on its native platform without modifying source code
or executables to include debug statements. The tool license
server was installed on the CoNNeCT software server in Building
142 and will be used in the CoNNeCT software development lab
in Building 333. Contact: Denise Varga/DPS, (216)
433-5190
Space Communications and Navigation (SCaN)
Systems Engineering Core Team (SECT)(Project Manager – Kul
B. Bhasin)
- Completed drafts of the Network Control (Section
4.5) and Testing, Training, Modeling, and Simulation (Section
4.8.6) sections of the SCaN System Requirements Document
- Participated in a Systems Engineering training
course entitled “Tracking and Communications Infrastructure
Systems Engineering” at JPL.
Space Networks Ground Segment Sustainment (SGSS)
(Project Manager – Kul B. Bhasin)
- Provided the architecture diagram set for review
to the SCaN TDRS Replenishment SGSS project
Upcoming Significant Events:
- Space Communications and Navigation (SCaN) Program
Management Review (PMR): February 5, 2009
- STS-119/15A Launch NET 2/19/09
CoNNeCT Preliminary Design Review (PDR) Kick-off: April
8-9, 2009 |